The complete case journey
Workflow
One connected flowchart from Applicant/Consultant login to environmental approval, operation and monitoring, including corrections, exceptional decisions, environmental audit and enforcement.
Read from top to bottom and follow the labelled arrows. Each box names the responsible role and required handoff. This is process guidance; the actions available on your case depend on its current stage, authority and activated controls.
- Regular workflow
- Correction or exception · dashed
- Separate activation required · dashed
- Classification needs resolution
Scroll horizontally and vertically to follow the complete diagram. Use zoom and section buttons for a closer view. Download keeps the whole chart on one scalable page.
Read the same workflow as linked text
Every diagram box and outgoing connection appears below. Follow the linked next steps to explore regular routes and exceptions.
- Applicant/Consultant login (regular). Use your existing applicant / consultant account. Select your authorized working role. Next: Create Case and intake form.
- EPA setup and staff access (regular). Administrator: accounts, offices and postings. Approved configuration / action grants required. Next: Assign review and requirements — Staff access; Vacancy, revocation or handover — Changed appointment.
- Create Case and intake form (regular). Proposed project: Schedule-I. Established project: Appendix-I + operation proof. Next: EPA screening / applicability.
- Screening clarification (exception). EPA records the required corrections. Applicant submits a successor intake revision. Next: EPA screening / applicability — Resubmit.
- EPA screening / applicability (regular). Assigned officer · verify commissioning and facts. Pin effective policy, category rule and evidence. Next: Which regulatory route?; Screening clarification — Corrections; Section 11 / 13 violation evidence — Recorded S11 / S13 violation.
- Classification cannot be resolved (blocked). Missing rule / conflict / ambiguous thresholds. No guessed category; obtain governed resolution.
- Which regulatory route? (regular). Proposed / commissioned from 11 Dec 2014:. assessment; before that date: audit policy. Next: GEA / IEE / EIA category recorded; Classification cannot be resolved — Unresolved; Environmental-audit route — Audit regime.
- GEA / IEE / EIA category recorded (regular). GEA Schedule IV · IEE III · EIA II. Pinned requirements, fee and assessment cycle. Next: Prepare prescribed filing; Responsible assessment office — Office routing.
- Responsible assessment office (regular). EIA: HQ review, Director HQ, DG final. IEE / GEA: appointed division or district issuer. Next: Assign review and requirements — Named authority.
- Environmental-audit route (conditional). Major / medium / minor · separate regime. Intake/classification needs approved activation. Next: Audit review-stage entry — Only when enabled.
- Prepare prescribed filing (regular). Applicant · Schedule VI and signed/stamped copy. Category report, GIS location and required files. Next: Lodge complete filing; Assessment fee and challan — Pay fee.
- Assessment fee and challan (regular). Applicant pays and uploads clean payment proof. Proof clears filing gate; not verified settlement. Next: Lodge complete filing — Clean proof; Finance verifies fee independently — Independent review.
- Lodge complete filing (regular). Applicant submits immutable filing snapshot. Required clean documents + payment gate. Next: EPA preliminary scrutiny.
- Incomplete filing returned (exception). EPA records deficiencies; applicant corrects. New filing revision and renewed scrutiny. Next: Prepare prescribed filing — Correct / re-lodge.
- EPA preliminary scrutiny (regular). Document checks, physical originals and copies. Compare exact lodged evidence and shortages. Next: Completeness confirmed; Incomplete filing returned — Incomplete.
- Finance verifies fee independently (regular). Accept / reject latest clean payment proof. Rejected proof: successor proof; filing retained. Next: Assessment fee and challan — Rejected: new proof.
- Completeness confirmed (regular). EPA confirms evidence / physical receipt gates. Start pinned category review clock. Next: Assign review and requirements; Audit review-stage entry — Audit cycle only.
- Audit review-stage entry (conditional). Governed audit cycle required; UAT may use fixture. Fixture does not supply intake authority. Next: Audit: CALL or WAIVE committee.
- Assign review and requirements (regular). Review manager assigns reviewer, GIS and field. Exact action authority and case scope required. Next: Project review committee meeting/presentation; Mandatory GIS review — Parallel GIS; Required field inspection — If required.
- Audit: CALL or WAIVE committee (conditional). DG / exact current office-order holder + reason. Active approved procedure or isolated UAT version. Next: CALL: committee meeting; Audit final action — WAIVE: DG only.
- Reschedule / minutes correction (exception). Reasoned successor appointment or minutes copy. Approval pins the latest clean minutes. Next: Project review committee meeting/presentation — Successor.
- Project review committee meeting/presentation (regular). Director schedules; reviewer records actual event. Attendance, minutes and Director approval. Next: Technical assessment and checklist; Reschedule / minutes correction — Reschedule / revise; Exceptional review committee meeting/presentation waiver — Exceptional request.
- Mandatory GIS review (regular). Assigned GIS officer · maps, layers and findings. Accepted evidence needed for readiness. Next: GIS evidence needs correction — Missing evidence; All technical evidence ready? — GIS accepted.
- CALL: committee meeting (conditional). Pinned roster, attendance, substitutions, recusals. Quorum, motion, votes, dissent and minutes. Next: Calculate committee result.
- Exceptional review committee meeting/presentation waiver (exception). DG / exact current WAIVE_PRESENTATION order. Reasoned waiver; ordinary Director cannot waive. Next: Technical assessment and checklist — Authorized waiver.
- GIS evidence needs correction (exception). Resolve missing layers, geometry or findings. Retain successor evidence; review remains blocked. Next: Mandatory GIS review — Recheck.
- Calculate committee result (conditional). Carried / defeated / tie under pinned procedure. Casting-vote treatment follows that version. Next: Audit final action; Quorum failure / new meeting — Quorum fails.
- Technical assessment and checklist (regular). Assigned reviewer checks category requirements. Optional proposed checklist is not extra authority. Optional legal / lab: three working days. Next: Technical observations (if needed); All technical evidence ready? — No observations.
- Required field inspection (regular). Assigned inspector · web / managed mobile. Capture findings and clean report; submit. Next: Director reviews field report — Submitted; Field visit not required / waived — Before submission only.
- Field visit not required / waived (exception). Director records lawful reason before submission. No waiver after submitted / returned / accepted. Next: All technical evidence ready? — Authorized waiver.
- Technical observations (if needed) (regular). EPA issues questions and a response deadline. Applicant / exact consultant replies + annexures. Next: Reviewer assesses each reply; No response after deadline — No response.
- Director reviews field report (regular). Accept or return for inspector correction. Submitted evidence cannot be replaced by waiver. Next: Required field inspection — Returned; All technical evidence ready? — Accepted.
- Quorum failure / new meeting (exception). Record reasons and a successor meeting. No carried resolution invented. Next: CALL: committee meeting — Successor meeting.
- Corrected technical reply (exception). Applicant reads EPA reason and submits successor. Earlier replies and assessments stay in history. Next: Reviewer assesses each reply — Successor reply.
- Reviewer assesses each reply (regular). Satisfactory: dispose observation with reasons. Un-satisfactory: applicant corrects and resubmits. Next: All technical evidence ready?; Corrected technical reply — Un-satisfactory.
- Audit final action (conditional). Authorized officer: carried committee outcome only. DG: override with reasons or direct WAIVE decision. Next: Approve / reject / resubmit report.
- No response after deadline (exception). EPA issues up to three append-only reminders. Closure only after all three and due-time gates. Next: Authorized non-response closure.
- Approve / reject / resubmit report (conditional). Select the matching Appendix VII branch. Final reasons and procedure remain pinned. Next: Prepare Appendix VII revision.
- Authorized non-response closure (exception). DG / exact authorized officer records reasons. No automatic approval or automatic closure. Next: Authorized reopening.
- All technical evidence ready? (regular). Reviewer checks review committee meeting/presentation, GIS, field and replies. Resolve requested advice or withdraw with reason. Next: Complete technical review.
- Authorized reopening (exception). Reasoned successor assessment cycle. Retain previous cycle; repeat required review. Next: Assign review and requirements — Successor cycle.
- Complete technical review (regular). Exact reviewer · record recommendation. GEA / IEE skip EIA hearing; EIA continues below. Next: EIA: initiate public hearing; Check readiness and start decision — GEA / IEE: no hearing.
- Prepare Appendix VII revision (conditional). DG / exact authorized officer · retained source. Approved renderer or visibly proposed UAT copy. Next: Generate and record signed scan.
- EIA: initiate public hearing (regular). Assigned Case Reviewer · governed hearing rule. Separate dedicated hearing assignment. Next: Approve date and notify applicant.
- Generate and record signed scan (conditional). Matching clean scan; authorized signatory. Original custody and service controls. Next: Issue Appendix VII and serve.
- Approve date and notify applicant (regular). Authorized Director / DG · future appointment. Retain notice and notification evidence. Next: Advertisements and invitations.
- Issue Appendix VII and serve (conditional). Hand delivery, diary acknowledgement and custody. Issue does not supply missing intake approval. Next: Resubmission branch — Resubmit branch; Audit approval: undertaking — Approval only; Audit decision retained — Rejection.
- Advertisement rejected / date change (exception). Correct proof and recheck governed notice interval. At least 15 calendar days from later publication. Next: Advertisements and invitations — Recheck proof/date.
- Advertisements and invitations (regular). Applicant uploads national/local advertisement proof. Reviewer accepts; retains departmental invitations. Next: Hold hearing; record actual event; Advertisement rejected / date change — Rejected / changed.
- Resubmission branch (exception). Pause remaining review clock at acknowledged service. Applicant submits clean successor report. Next: Authorized acceptance of successor — Clean report.
- Hold hearing; record actual event (regular). Attendance, public submissions and signed minutes. Video delivered once on CD / flash drive. Next: Hearing observations and replies.
- Authorized acceptance of successor (conditional). Resume remaining review clock in same cycle. Repeat committee review; preserve earlier decision. Next: Audit: CALL or WAIVE committee — Same-cycle review.
- Un-satisfactory / absent hearing reply (exception). Successor reply assessed again; non-response uses. the same reminder / closure / reopening controls. Next: Hearing observations and replies — Corrected reply; No response after deadline — Absent reply.
- Hearing observations and replies (regular). Written clarification + optional annexure. Reviewer assesses replies and verifies video receipt. Next: Complete hearing review; Un-satisfactory / absent hearing reply — Correction / delay.
- Complete hearing review (regular). Mandatory notice, event, reply and receipt gates. Incomplete evidence returns to its responsible task. Next: Check readiness and start decision.
- Audit approval: undertaking (conditional). Applicant submits dated stamp-paper undertaking. Audit rejection has no undertaking path. Next: Audit decision retained.
- Check readiness and start decision (regular). Exact Case Reviewer · all required gates complete. Creates decision-preparation task. Next: Approve decision preparation.
- Audit decision retained (conditional). Approval / rejection and service evidence preserved. Appendix VIII runtime remains unavailable.
- Approve decision preparation (regular). Authorized review manager / Director HQ for EIA. Historical cases keep their pinned earlier route. Next: Prepare approval or rejection.
- Prepare approval or rejection (regular). Reviewer · VII EIA / VIII IEE / IX GEA. Approval conditions; rejection has no conditions. Next: Submit revision and generate PDF.
- Missing retained data / render error (exception). Correct configuration or return submitted revision. Successor render; never rewrite submitted evidence. Next: Prepare approval or rejection — Returned successor.
- Submit revision and generate PDF (regular). Filed details, office and current signatory pinned. Controlled template; HTTPS QR on every page. Next: Wet signature, seal and clean scan; Missing retained data / render error — Blocked generation.
- Wet signature, seal and clean scan (regular). DG signs EIA; named current issuer signs IEE/GEA. Custody, certified copy and exact page matching. Next: Competent issuer authorizes.
- Returned decision / changed signer (exception). Issuer records reason; preparer submits successor. New render and signature; preserve prior revision. Next: Prepare approval or rejection — Successor revision.
- Issued rejection (regular). Applicant acknowledges protected decision. No approval-only monitoring / undertaking.
- Issue and applicant acknowledges (regular). Protected issued copy, signature and service record. Approval opens compliance; rejection ends route. Next: Issued rejection — Rejection; Public verification (if activated) — Approved public fields; Approval conditions: Schedule X; Record construction commencement — No conditions.
- Public verification (if activated) (conditional). QR exposes only approved disclosure snapshot. Full decision stays protected.
- Undertaking returned / unavailable (exception). Correct and resubmit when authorized. Missing controlled source blocks affected action. Next: Approval conditions: Schedule X — Clean successor.
- Approval conditions: Schedule X (regular). Applicant: stamp-paper / signer / witnesses. Clean successor + original receipt; officer accepts. Next: Record construction commencement; Undertaking returned / unavailable — Return / blocked.
- Section 11 / 13 violation evidence (regular). Officer records violation and evidence references. Penalty does not change the assessment case state. Next: DG or exact penalty delegation — Authority check.
- Pre-commencement extension request (exception). Applicant: reasons, change statement and proof. DG decides grant / refuse / fresh assessment. Next: Record construction commencement — Granted; Refused / commencement expired — Refuse / expiry.
- Record construction commencement (regular). Applicant records actual date within validity. Condition follow-up due quarterly after issue. Next: Report construction completion; Pre-commencement extension request — Before commencement.
- Authorize and serve Form A (conditional). Reasons, severity, allowed amount and clean form. DG / exact delegate re-authenticates; service proof. Next: Proponent responds to Form A.
- Enter amount and take penalty action (regular). Officer enters PKR amount, reasons and directions. Re-authenticate and record the action. Next: Applicant reads the recorded action — Saved action.
- Refused / commencement expired (exception). No commencement beyond current valid deadline. Fresh assessment direction requires new case. Next: Create Case and intake form — Fresh assessment: new case.
- Report construction completion (regular). Applicant: actual completion date, report, declaration. Compliance request sent to responsible Director. Next: Director assigns monitoring inspector.
- Proponent responds to Form A (conditional). Accept or reject the served proceeding. No assumed response or automatic penalty payment. Next: Accepted → authorize Form B; Rejected → court referral — Rejected.
- Applicant reads the recorded action (regular). Amount, reasons, directions and officer retained. No automatic payment, service or court filing.
- Director assigns monitoring inspector (regular). Exact inspector and instructions; retained task. Responsible office retains compliance ownership. Next: Inspector verifies every EA condition.
- Accepted → authorize Form B (conditional). DG / exact delegate · controlled penalty demand. Form B only after recorded acceptance. Next: Finance generates 1Link demand.
- Rejected → court referral (conditional). DG / exact delegate records referral packet. No Form B or payment on rejected branch. Next: Append court events / outcome.
- Inspector verifies every EA condition (regular). Satisfactory / Un-satisfactory findings per condition. Clean report submitted to Director. Next: Director decides compliance.
- Finance generates 1Link demand (conditional). Live certified adapter or isolated UAT sandbox. Stable payment identity and replay-safe requests. Next: Finance reconciles provider payment.
- Append court events / outcome (conditional). Authorized filing, service and outcome evidence. Prior proceeding history remains immutable.
- Correct compliance deficiencies (exception). Applicant reads reasons and submits new evidence. New request; Director assigns inspector again. Next: Report construction completion — Corrected request.
- Director decides compliance (regular). Confirmed / not confirmed / returned for information. Confirmation needs all conditions satisfactory. Next: Written confirmation → operation; Correct compliance deficiencies — Return / not confirmed.
- Finance reconciles provider payment (conditional). Verified callback / ledger reconciliation. Payment must bind to exact demand and amount. Next: Penalty payment recorded; Payment pending / mismatch / outage — Not reconciled.
- Payment pending / mismatch / outage (exception). Finance investigates and retries exact demand. No settlement claim until verified reconciliation. Next: Finance generates 1Link demand — Investigate / exact retry.
- Written confirmation → operation (regular). Applicant records actual operational commencement. Only after clean written compliance confirmation. Next: Recurring reports and condition evidence.
- Penalty payment recorded (conditional). Immutable settlement and proceeding evidence. Does not itself approve the environmental case.
- Recurring reports and condition evidence (regular). Applicant: six-month operational reports. Quarterly condition follow-up / supporting files. Next: Authorized compliance review.
- Report / condition evidence returned (exception). Applicant corrects via successor submission. Final non-compliance remains recorded. Next: Recurring reports and condition evidence — Successor report.
- Authorized compliance review (regular). Accept / return / final non-compliance finding. Retain reasons and authorized evidence history. Next: Continue monitored operation; Report / condition evidence returned — Return; Section 11 / 13 violation evidence — S11 / S13 trigger only.
- Continue monitored operation (regular). Repeat due reports, inspections and condition checks. Persistent case and evidence history. Next: Internal reporting / Schedule XI check; Recurring reports and condition evidence — Next reporting period.
- Internal reporting / Schedule XI check (regular). Scoped source-field reconciliation and gaps. Not official statutory register or approved export. Next: Controls apply to EVERY step.
- Pending / unsafe upload (exception). Wait for clean verdict; error: authorized rescan. Rejected file: permitted successor, retain history.
- Controls apply to EVERY step (regular). Wrong role / scope / assignment: deny. Stale version: refresh; exact retry: same result. Next: Pending / unsafe upload — All uploads; Notifications / provider outage — All side effects.
- Notifications / provider outage (exception). Portal tasks remain visible; retry delivery safely. Unavailable required provider blocks its own action. Next: Field offline / sync conflict — Field sync.
- Field offline / sync conflict (exception). Exact durable retry IDs; clean-file finalization. Expired/revoked package: reconcile, no forced submit.